Extension of the wastewater treatment plant in Wielki Klincz
Wielki KlinczKościerzyna Municipalty
Photo gallery: 1 of 5
Photo gallery: 3 of 5
2021 - 2022
Investor: Municipal Engineering Authority of Kościerzyna Municipality
Investment value: 6 749 231,60 PLN
Investment type: build
Technology type: SBR tank
Realization description
Scope of investment:
- Conversion of three existing aerobic sludge stabilisation tanks with an active volume of 115 m³ into SBR reactors in terms of equipment and installation (without purchasing equipment and automation);
- construction of a DN250 gravity sewer section together with the removal of the existing section colliding with the newly designed facility;
- shed with sludge storage area;
- construction of “A” emergency overflow on the gravity sewer system before the raw sewage pumping station;
- diversion all wastewater flowing into the treatment plant to a retention pond;
- construction of “B” emergency overflow to the mechanical part of the treatment plant;
- construction of an aerobic activated sludge stabilisation chamber;
- construction of a roofed sludge storage facility;
- construction of a chamber with flow measurement of the treated wastewater on the effluent collector from the treatment plant;
- alignment of roads and pavements with the new facilities;
- reconstruction of the fence.