Extension of the wastewater treatment plant in Wielki Klincz

Wielki Klincz
Kościerzyna Municipalty

...

Extension of the wastewater treatment plant in Wielki Klincz

rozbudowa-oczyszczalni-sciekow-w-miejscowosci-wielki-klincz-5

Photo gallery: 1 of 5

2021 - 2022

Investor: Municipal Engineering Authority of Kościerzyna Municipality

Investment value: 6 749 231,60 PLN

Investment type: build

Technology type: SBR tank

Realization description

Scope of investment:

  • Conversion of three existing aerobic sludge stabilisation tanks with an active volume of 115 m³ into SBR reactors in terms of equipment and installation (without purchasing equipment and automation);
  • construction of a DN250 gravity sewer section together with the removal of the existing section colliding with the newly designed facility;
  • shed with sludge storage area;
  • construction of “A” emergency overflow on the gravity sewer system before the raw sewage pumping station;
  • diversion all wastewater flowing into the treatment plant to a retention pond;
  • construction of “B” emergency overflow to the mechanical part of the treatment plant;
  • construction of an aerobic activated sludge stabilisation chamber;
  • construction of a roofed sludge storage facility;
  • construction of a chamber with flow measurement of the treated wastewater on the effluent collector from the treatment plant;
  • alignment of roads and pavements with the new facilities;
  • reconstruction of the fence.