Reconstruction and modernisation of the municipal wastewater treatment plant in Wójtówka

Wójtówka
Waganiec Municipality

...

Reconstruction and modernisation of the municipal wastewater treatment plant in Wójtówka

przebudowa-i-modernizacja-gminnej-oczyszczalni-sciekow-w-miejscowosci-wojtowka-1

Photo gallery: 1 of 5

2023 - 2024

Investor: Waganiec Municipality

Investment value: 2 031 579,95 PLN

Investment type: build

Technology type: Flow-through

Realization description

Stage I

  • Reactor refurbishment: cleaning, repair of wear and material losses, insulation and scraper overhaul.
  • Renovation of the equalising tank: cleaning, refilling gaps and providing insulation for the equalising tank, which changed its technological function after reconstruction and now serves as an equalising/emergency tank.
  • Replacement of worn-out technological equipment and fittings: pumps, mixers, flow meters, probes and sensors.
  • Construction of a bypass for the duration of reactor refurbishment.
  • Delivery of a wastewater receiving station.
  • Technological commissioning of the treatment plant after reconstruction.

Stage II

  • Renovation of the social and technical building.
  • Modernisation and maintenance by means of protective coatings on external concrete surfaces, including repair of defects – facilities within the treatment plant, i.e. reactor, equalisation/emergency tank, grit separators, multifunctional pumping station, manholes, etc.
  • Replacement of wall-mounted axial fans in the screening station, including installation of new power supply and control cabinet.
  • Provision of equipment: pumps, mixers, two compression stages for blowers.
  • Installation of a containerised wastewater receiving station, delivered in stage I, including the construction of a drive-on slab and service connections at the P7 Plebanka network sewage pumping station.
  • Inspection, testing and adjustment of roof fans, including replacement of ventilation ducts in the screen station.
  • Disassembly of the lime tank and replacement of the sanitisation line – disassembly of worn-out equipment, delivery and installation of the sanitisation line and polyelectrolyte tank.
  • Installation of a steel platform and steel supports for mounting a new lime tank and installation of a protective railing around the stainless steel acid-resistant tank in the dewatering station room.
  • Delivery and assembly of the blower.
  • Repairs: guard rails at existing structures and garage facade.
  • Replacement of the gate, construction of a driveway, replacement of the basket grate, assembly of a DN 400 gate valve, and installation of lighting and monitoring at the P7 pumping station.
  • Replacement of electrical boxes for local control of equipment.
  • Construction of stairs and a walkway to the measuring well.
  • Implementation of automated power generator activation along with reconstruction of the facility’s electrical power supply system.
  • Configuration of the newly installed equipment with the existing instrumentation and control system.