Reconstruction of the band pumping station in Frelichów

Frelichów
Chybie Municipality

...

Reconstruction of the band pumping station in Frelichów

przebudowa-pompowni-opaskowej-frelichow-1

Photo gallery: 1 of 4

2021 - 2022

Investor: Górnośląskie Przedsiębiorstwo Wodociągów S.A., Katowice

Investment value: 5 195 907,25 PLN

Investment type: build

Realization description

Scope of implementation:

  • Replacement of three pumps of 0.1 m³/s and 0.5 m³/s, which together are expected to increase the pumping capacity of the pumping station to 1.1 m³/s;
  • renovation of discharge pipelines by introducing UV-cured resin sleeves;
  • replacement of ND400 and DN200 facility pipelines;
  • installation of shut-off fittings on each pressure pipe;
  • reconstruction of 3 pumping chambers;
  • renovation of all concrete structures within the pool;
  • renovation of the building exterior and interior;
  • modernisation of the transformer station;
  • replacement of the 15kV overhead power line;
  • implementation of instrumentation for the pumps;
  • implementation of a monitoring system including a telemetry system.