Restoration of the main industrial and rainwater pumping station for PGE GiEK SA Dolna Odra Power Plant Branch
Nowe CzarnowoGryfino Municipality
Photo gallery: 1 of 5
Photo gallery: 3 of 5
2023 - 2024
Investor: PGE Górnictwo i Energetyka Konwencjonalna SA, Dolna Odra Power Plant Branch
Investment value: 11 618 334,00 PLN
Investment type: build
Realization description
The project included the refurbishment of the pumping station and its process installations, involving the replacement of the following components with new ones:
- rainwater pumps,
- industrial wastewater (sanitary sewage) pumps to monoblock pumps,
- pipelines, barrier and backflow fittings on suction and discharge pipelines of rainwater and sanitary systems,
- pipelines, barrier and backflow fittings on domestic and firefighting water pipelines,
- sanitary sewer pipes (replacement with plastic pipes),
- piping and radiators of the central heating system.
The pumping station was fitted with mechanically driven automatic grates.
Refurbishment work was also carried out at the pumping station in relation to:
- sanitary installation,
- firefighting water installation,
- central heating installation,
- mechanical ventilation installation.