Reconstruction and extension of the municipal waste water treatment plant in Cielądz
Photo gallery: 1 of 2
Photo gallery: 2 of 2
Paweł Królak
Mayor of Cielądz Municipality
Contract of 11.09.2024
Investor: Cielądz Municipality
Investment value: 6 783 584,06 PLN
Investment type: design and build
Technology type: Flow-through
Realization description
1. Building and technology works:
- Extension of the existing treatment plant with additional process lines.
- Construction of a new SBR-type biological reactor.
- Construction of an effluent separation chamber, averaging chamber and sludge tank.
2. Modernisation of existing facilities:
- Replacement and modernisation of pretreatment equipment: grate, grit chamber.
- Upgrade of the aeration chamber and secondary settling tanks.
- Reconstruction of the sludge system (thickening, stabilisation, dewatering).
3. Supply and installation of process equipment:
- Pumps, blowers, mixers, valves, stainless steel pipework.
- Automatic gate valves, level sensors, flow meters.
5. Land development:
- Access roads, fencing, site lighting.
- Drainage and storm sewers.
6. Power supply and renewable energy sources:
- Photovoltaic (PV) installation for the treatment plant’s own needs.
7. Documentation and acceptance:
- Execution of detailed and as-built design.
- Obtaining all required permits, notifications and acceptances.
Technical parameters after modernisation: throughput: up to 500 m³/d, PE: approx. 2 500.